Construction Travel Impacts
Current Closures
I-5 Northbound and Southbound Closure: July 11-12
All lanes of Interstate 5 northbound and southbound in the Rose Quarter will close overnight for up to 14 hours July 11-12 to install a new overhead sign structure near the Oregon Convention Center.
The closures will begin at 10 p.m. Saturday, July 11, and end by noon Sunday, July 12.
I-5 northbound closure:
- All lanes of I-5 northbound will be closed beginning at Exit 300 to I-84 eastbound. Access to I-84 eastbound will remain open.
- The ramp from NE Broadway to I-5 northbound will stay open. All lanes of I-5 northbound will be open beyond this point.
I-5 southbound closure:
- All lanes I-5 southbound will be closed beginning at Exit 302B to I-405 (Fremont Bridge). Access to I-405 will remain open.
- Drivers on I-84 westbound will be directed to I-5 southbound. All lanes of I-5 southbound will remain open beyond that point.
Plan ahead and expect delays:
- Use the signed detour at I-405 for local travel northbound or southbound.
- Use I-205 for regional travel.
- Plan your trip ahead of time and access travel online navigation tools like ODOT’s Get There Oregon and TripCheck.
- Consider altering your travel time, rescheduling appointments to before or after the closure or avoiding us of a personal vehicle.
- Consider a different way to travel like MAX, streetcar, bus, bike, walk, or carpool.
Sign up for Rose Quarter Construction text alerts to be notified when the highway reopens. Call (503) 276-7808 to submit noise concerns.

Local Street Closure: NE Lloyd Boulevard
- The closure will begin at 10 p.m. on Saturday, July 11 to 8 a.m. on Sunday, July 12
- Vehicles will be required to detour. Detour routes will be clearly signed.
- Access to the Oregon Convention Center along Lloyd Boulevard from the east and along NE 1st Avenue will be maintained.
- Pedestrians and bicyclists will be able to pass through using the wide sidewalk along the southbound lane.

Intermittent Overnight Closures: I-5 Southbound Right Lane
Purpose: The right lane of I-5 southbound will close overnight intermittently between the Moda Center and Morrison Bridge exit for upgrades to the bridge railing.
Where:
- I-5 southbound right lane between Oregon Convention Center and Morrison Bridge
Closure Details:
- Intermittent closures will take place between 10 p.m. to 5 a.m.
- I-5 southbound right lane between Moda Center and Morrison Bridge will be closed during periodically in July.
Detours Required:
- Travelers heading south on I-5 will be able to use the open lane.

Major Closures Coming Summer and Fall 2026
I-5 Northbound and Southbound Closure: July 11-12, 2026*
14-Hour Full Closure
Click here to view the I-5 Sign Structure Closure Fact Sheets available in English, Spanish, Chinese, Russian and Vietnamese
Expect delays. Plan Ahead. *Dates subject to change.
- All lanes of I-5 northbound and southbound will be closed overnight for up to 14 hours from 10 p.m. on Saturday, July 11 to noon on Sunday, July 12.*
- The detour for I-5 travel in both directions will be I-405.
- During the closure, crews will remove an existing sign structure and install a new sign structure (the “sign bridge”) near the Oregon Convention Center.
Exits that will be open and closed during this closure:
- I-5 southbound to be closed beginning at Exit 302B to the Fremont Bridge and I-405
- I-5 northbound to be closed beginning at Exit 300 to I-84
- I-405 is the detour route around the closure
- I-84 westbound will be routed to I-5 southbound. Drivers will detour onto I-405 to access I-5 northbound.
- Ramp to I-84 eastbound from I-5 northbound will remain open. Ramp from I-84 westbound to I-5 southbound to remain open. All lanes of I-5 southbound will be open beyond this point.
- Ramp from Broadway to I-5 northbound to remain open. All lanes of I-5 northbound will be open beyond this point.
I-5 Southbound Closure Beginning September 11, 2026
24 hours, 7 days a week for up to 5 weeks
Plan ahead. Significant delays and unpredictable travel times are expected.
- Crews will repair and reinforce weak areas, replace bridge joints, repave the surface and repaint lane lines on the highway.
- Travel times may take two to three times longer than usual.
- Congestion could back up across the Columbia River into Washington and onto local streets in the Portland area.
- The highway will reopen as soon as the work is complete.
Drivers can expect:
- I-5 southbound to be closed between I-405 and I-84.
- I-5 southbound travel to be detoured to I-405 southbound. Regional traffic to be directed to I-205.
- One lane to the Broadway/Weidler exit to remain open for local and event center access.
- On-ramps from Greeley, I-405 northbound/Fremont Bridge and the Moda Center to I-5 southbound to be closed.
- I-5 southbound ramp to I-84 eastbound to be closed.
- I-84 westbound to I-5 southbound to remain open.
- I-5 northbound to remain open.
Learn more by viewing our project fact sheets
Click here to view the I-5 Southbound Closure Fact Sheets available in English, Spanish, Chinese, Russian and Vietnamese
I-5 Southbound Closure Overview Fact Sheet
- I-5 Southbound Closure Overview Fact Sheet: English
- I-5 Southbound Closure Overview Fact Sheet: Spanish
- I-5 Southbound Closure Overview Fact Sheet: Chinese
- I-5 Southbound Closure Overview Fact Sheet: Vietnamese
- I-5 Southbound Closure Overview Fact Sheet: Russian
I-5 Southbound Closure Decision Fact Sheet
To stay informed about upcoming construction and travel impacts, sign up for travel alerts or visit TripCheck to get real-time travel information in the project area.