Construction Travel Impacts

Get Construction & Travel Alerts

 

 

Current Closures

I-5 Northbound and Southbound Closure: July 11-12

All lanes of Interstate 5 northbound and southbound in the Rose Quarter will close overnight for up to 14 hours July 11-12 to install a new overhead sign structure near the Oregon Convention Center. 

The closures will begin at 10 p.m. Saturday, July 11, and end by noon Sunday, July 12.  

I-5 northbound closure:

  • All lanes of I-5 northbound will be closed beginning at Exit 300 to I-84 eastbound. Access to I-84 eastbound will remain open.
  •  The ramp from NE Broadway to I-5 northbound will stay open. All lanes of I-5 northbound will be open beyond this point. 

I-5 southbound closure:

  • All lanes I-5 southbound will be closed beginning at Exit 302B to I-405 (Fremont Bridge). Access to I-405 will remain open.
  • Drivers on I-84 westbound will be directed to I-5 southbound. All lanes of I-5 southbound will remain open beyond that point.

Plan ahead and expect delays:

  • Use the signed detour at I-405 for local travel northbound or southbound.
  • Use I-205 for regional travel.
  • Plan your trip ahead of time and access travel online navigation tools like ODOT’s Get There Oregon and TripCheck.
  • Consider altering your travel time, rescheduling appointments to before or after the closure or avoiding us of a personal vehicle.
  • Consider a different way to travel like MAX, streetcar, bus, bike, walk, or carpool.

Sign up for Rose Quarter Construction text alerts to be notified when the highway reopens. Call (503) 276-7808 to submit noise concerns.

Closure and detour map for I-5 showing southbound closures beginning at Exit 302B near the I-405 Fremont Bridge and northbound closures beginning at Exit 300 near the I-84 ramp. I-84 eastbound access and I-5 northbound at the Broadway on-ramp are shown as open. I-84 westbound traffic will be detoured to I-5 southbound. The map shows I-405 as the primary detour around the I-5 closure.

Local Street Closure: NE Lloyd Boulevard

Purpose: Both directions of NE Lloyd Boulevard will be closed for structural work underneath I-5.
 
Where: NE Lloyd Boulevard between NE 1st Street and NE Oregon Street.  
 
Closure Details:
  • The closure will begin at 10 p.m. on Saturday, July 11 to 8 a.m. on Sunday, July 12
Detours Required:
  • Vehicles will be required to detour. Detour routes will be clearly signed. 
  • Access to the Oregon Convention Center along Lloyd Boulevard from the east and along NE 1st Avenue will be maintained.
  • Pedestrians and bicyclists will be able to pass through using the wide sidewalk along the southbound lane.  

Intermittent Overnight Closures: I-5 Southbound Right Lane

Purpose: The right lane of I-5 southbound will close overnight intermittently between the Moda Center and Morrison Bridge exit for upgrades to the bridge railing. 

Where: 

  • I-5 southbound right lane between Oregon Convention Center and Morrison Bridge

Closure Details:

  • Intermittent closures will take place between 10 p.m. to 5 a.m.  
  • I-5 southbound right lane between Moda Center and Morrison Bridge will be closed during periodically in July. 

Detours Required: 

  • Travelers heading south on I-5 will be able to use the open lane. 

Major Closures Coming Summer and Fall 2026

I-5 Northbound and Southbound Closure: July 11-12, 2026*

14-Hour Full Closure

Expect delays. Plan Ahead. *Dates subject to change.

  • All lanes of I-5 northbound and southbound will be closed overnight for up to 14 hours from 10 p.m. on Saturday, July 11 to noon on Sunday, July 12.*
  • The detour for I-5 travel in both directions will be I-405.
  • During the closure, crews will remove an existing sign structure and install a new sign structure (the “sign bridge”) near the Oregon Convention Center.

Exits that will be open and closed during this closure:

  • I-5 southbound to be closed beginning at Exit 302B to the Fremont Bridge and I-405
  • I-5 northbound to be closed beginning at Exit 300 to I-84 
  • I-405 is the detour route around the closure 
  • I-84 westbound will be routed to I-5 southbound. Drivers will detour onto I-405 to access I-5 northbound.  
  • Ramp to I-84 eastbound from I-5 northbound will remain open. Ramp from I-84 westbound to I-5 southbound to remain open. All lanes of I-5 southbound will be open beyond this point.  
  • Ramp from Broadway to I-5 northbound to remain open. All lanes of I-5 northbound will be open beyond this point. 

I-5 Southbound Closure Beginning September 11, 2026

24 hours, 7 days a week for up to 5 weeks

Plan ahead. Significant delays and unpredictable travel times are expected.

  • Crews will repair and reinforce weak areas, replace bridge joints, repave the surface and repaint lane lines on the highway.
  • Travel times may take two to three times longer than usual.
  • Congestion could back up across the Columbia River into Washington and onto local streets in the Portland area. 
  • The highway will reopen as soon as the work is complete. 

Drivers can expect:  

  • I-5 southbound to be closed between I-405 and I-84.
  • I-5 southbound travel to be detoured to I-405 southbound. Regional traffic to be directed to I-205.  
  • One lane to the Broadway/Weidler exit to remain open for local and event center access. 
  • On-ramps from Greeley, I-405 northbound/Fremont Bridge and the Moda Center to I-5 southbound to be closed.
  • I-5 southbound ramp to I-84 eastbound to be closed.
  • I-84 westbound to I-5 southbound to remain open. 
  • I-5 northbound to remain open.

Learn more by viewing our project fact sheets

 

To stay informed about upcoming construction and travel impacts, sign up for travel alerts or visit TripCheck to get real-time travel information in the project area.