Construction Travel Impacts
I-5 SOUTHBOUND IS OPEN AS OF OCT. 8!
Click here to view maps in Spanish, Chinese, Russian and Vietnamese
Update as of Oct. 8: Southbound I-5 in the Rose Quarter and on- and off-ramps in the work zone have reopened, sooner than estimated. Expect occasional ramp and lane closures as we restore lane striping, barriers and other traffic controls to their original configuration.
Please watch out and slow down for crews still working to restore signs, other traffic control and continuing work on the project.
For the latest information on the closure reopening, view our newsletter and tell us how we did by taking our survey.
Plan ahead. Significant delays and unpredictable travel times are expected.
- Travel times may take two to three times longer than usual.
- Congestion could back up across the Columbia River into Washington and onto local streets in the Portland area.
- If you need additional resources to help you get around during major closures or to communicate information with your network, visit our Closure Travel Resources or I-5 Closures Toolkit pages.
Drivers can expect
Drivers can expect:
- I-5 southbound is closed between I-405 and I-84
- This closure is all hours of the day from September 11 to early October
- One lane is maintained from the split with I-405 to the Broadway/Weidler off-ramp to provide access to the Rose Quarter events district, the Moda Center and the Oregon Convention Center
- I-5 northbound remains open at all times
- I-5 southbound is expected to be completely closed starting at about 10 p.m. on Friday, September 11. However, there may be I-5 ramps that could start to close an hour earlier at 9 p.m. Travelers are encouraged to allow extra time to get where you need to go and consult navigation tools to plan your route.
- The highway will reopen as soon as the work is complete.
How will staged tows work during the closure?
- Vehicles involved in an incident or stalled within the project boundaries do not have the preference of selecting a tow service provider. These vehicles will be towed by the project staged towing contractor selected by ODOT.
- ODOT will be towing all abandoned vehicles within the project boundaries using the staged towing contractor.
- All tows taken by staged towing contractor will be at owners expense.
Closed Ramps
- Onramp from Alberta St to I-5 SB: CLOSED
- Onramp from I-405 NB to I-5 SB: CLOSED
- Onramp from Greeley Ave to I-5 SB: CLOSED
- Onramp from Wheeler/Williams/Ramsay at the Moda Center to I-5 SB: CLOSED
- Offramp from I-5 SB to I-84 EB: CLOSED
- Offramp from I-5 SB to Morrison Bridge: CLOSED
Open Ramps
- Onramp from Rosa Parks Way to I-5 SB: OPEN
- Onramp from Going St to I-5 SB: OPEN
- Offramp from I-5 SB to Broadway: OPEN
- Onramp from I-84 WB to I-5 SB: OPEN
- Offramp from I-84 WB to Morrison Bridge: OPEN
Click here to view the I-5 Southbound Closure Fact Sheets available in English, Spanish, Chinese, Russian and Vietnamese
I-5 Southbound Closure Overview Fact Sheets with Maps
- I-5 Southbound Closure Overview Fact Sheet: English
- I-5 Southbound Closure Overview Fact Sheet: Spanish
- I-5 Southbound Closure Overview Fact Sheet: Chinese
- I-5 Southbound Closure Overview Fact Sheet: Vietnamese
- I-5 Southbound Closure Overview Fact Sheet: Russian
I-5 Southbound Closure Decision Fact Sheet
To stay informed about upcoming construction and travel impacts, sign up for travel alerts or visit TripCheck to get real-time travel information in the project area. For information on traffic impacts associated with other ODOT construction projects visit TripCheck.
Additional Closures
Sidewalk Closure: NE Oregon St
- The closures will be in place 24 hours a day from Sept. 21 to Oct. 11
- No detours are required.

Overnight Closures: I-5 Northbound Right Lane
- I-5 northbound right lane between Exit 302C to Greeley Ave and the I-405 on-ramp
Closure Details:
- Closures will take place on the nights of Sept. 28-Oct. 6
- Closures will be overnight between 10 p.m. to 5 a.m.